Skip to content

American Society of Civil EngineersASCE Met Section

Advertisement
Home arrow Met Section arrow Awards arrow Construction Achievement Project
Construction Achievement Project of the Year Award Print E-mail
This award is presented for a major construction project completed within the past year within the New York metropolitan area. The Construction Achievement Award was instituted by the Metropolitan Section in 1966.

2011 Recipient:

Madison Avenue Trenchless Technology

Owner
New York City Department of Design and Construction and New York City Department of Environmental Protection

Contractor
Halcyon Construction Corp.

Designer
New York City Department of Design and Construction

Research & Development
Polytechnic Institute of NYU, Urban Utility Center

Construction Inspection
HAKS

Trenchless technology was at the center of a $14 million pilot program to reline 11,000 feet of existing, 115-year-old 48-inch cast iron water main on Madison Avenue in midtown Manhattan. The project owner is the New York City Department of Design and Construction Infrastructure Division (NYCDDC) and the New York City Department of Environmental Protection (NYCDEP). The design was by NYCDDC, in a research and development collaborative effort with the Urban Utility Center at the Polytechnic Institute of NYU. The contractor for the project was Halcyon and construction inspection was performed by HAKS. The project was the first of its kind to employ trenchless technology on a large diameter trunk water main in NYC and the program was in the heart of New York City's Central Business District. It was, in addition, one of the largest trenchless technology projects ever accomplished. While the main focus of the project was on extending the life and reliability of the 48-inch trunk main, at the same time it sought to assess the performance and future applicability of trenchless technology. The project also involved installing 1,000 feet of new 48-inch and 36-inch steel water mains, various sized distribution water mains, new curbs, sidewalks and 11,500 feet of roadway paving. Project limits extended along Madison Avenue from East 37th to East 78th Street. Work began in January 2008 and was completed in September 2010.

The particular lining process had not been used before in New York City. It made use of Insituform's Polyfold, a high-density polyethylene (HDPE) plastic lining material to stop joint leakage that could eventually lead to failure of the trunk main in the future. The 50-foot long liner segments were butt fused into longer, predetermined lengths as needed for insertion into the main. Installing the liner was done at staging and receiving pits, spaced three blocks apart, which were dug down from the street to the water main.

At the staging pit the compressed plastic liner was inserted into the pipe, winched through from the receiving pit with the aid of bentonite spray to reduce friction, then positioned and expanded into place inside the pipe. Compared to digging through the street and trenching from the surface down to the main to do the work, trenchless technology relied on only relatively few, discrete access points from the street to the underground main, which significantly impacted the work that would otherwise have had to be done. Trenching would have required increased time and cost for excavation and trench shoring, and for securing or relocating utilities that would be in the path of the excavations. It would have required lane closures, traffic detours, rerouting of transit buses, and pedestrian detours. In general, the trenchless approach to relining the water main had only a minimum impact on the activities going on in the congested Madison Avenue business district, with its heavy pedestrian, vehicular, commercial and residential traffic. Successful completion of the trunk main relining using trenchless technology clearly met the objectives of NYCDDC and exceeded the Department’s needs. It provided a means to extending the aging, local water supply infrastructure at relatively low cost compared to complete reconstruction, and assured the continued, long term reliability of the trunk main into the future. Trenchless technology greatly minimized lane closures, traffic interruptions and detours, and reduced the need for relocating utilities. This in turn shortened the project duration and lowered its costs.

Past Recipients:

2010 Gowanus Expressway Viaduct Rehabilitation
Owner: New York State Department of Transportation
Contractor: DeFoe Corp.
Designer: Bechtel/Charles H. Sells/URS Tri-Venture
Resident Engineering: HAKS/AECOM, JV
2009 Realignment of Drury Lane and Construction of a New Access Road to Stewart International Airport
Owner: New York State Department of Transportation
Contractor: Lancaster Development, Inc.
Designer: Berger Lehman Associates, P.C.
Resident Engineering: HAKS/AECOM, JV
2008 FDR Drive – East 54th Street to 63rd Street and Outboard Detour Roadway
Owner: New York State Department of Transportation
Contractor: Slattery Skanska/Weeks Marine, JV
Designer: HDR|Daniel Frankfurt
Resident Engineering: Jacobs Edwards and Kelcey/URS, JV
2007 Route 9A Promenade South Project
Owner: New York State Department of Transportation
Contractor: Conti of New York, LLC
Designer: Vollmer Associates
Resident Engineering: DMJM+Harris (prime), The RBA Group, KS Engineering
2006 Reconstruction of the Brooklyn-Queens Expressway from Broadway to 25th Street
Owner: New York State Department of Transportation
Contractor: Slattery Skanska, Inc.
Designer: URS Corporation/Dewberry
Resident Engineer: Parsons Brinckerhoff Quade & Douglas, Inc.
2005 LIE/Cross Island Parkway Interchange Improvement Project
Owner: New York State Department of Transportation
Contractor: Perini Corporation
Engineer: Vollmer Associates
2004 Reconstruction of the Bruckner Interchange
Owner: New York State Department of Transportation
Contractor: Defoe Corporation
Construction Management: HAKS Engineers (Prime Consultant), Edwards & Kelcey Engineers, Inc, (Subconsultant)
2003 Reconstruction of Route 9A from 57th Street to Battery Place
Owner: New York State Department of Transportation
Contractors: Tully Construction, Perini Corporation, Felix Equities, Grace Industries, and Yonkers Construction
2002 CUNY, Baruch College New Vertical Campus
Owner: Dormitory Authority of the State of New York
Contractor: TDX Construction Corp.
2001 Williamsburg Bridge Contract 6, Transit Structure
New York City Department of Transportation
Parsons Transportation Group
Slattery Skanska
2000 63rd Street Tunnel Connector
Slattery Skanska, Inc.
1999 Reconstruction of the Williamsburg Bridge South Roadways
Perini/O&G II (Joint Venture)
1998 Fordham Plaza Bridge
Slattery Skanska, Inc.
1997 New York Hospital Expansion Project
Lehrer McGovern Bovis
1996 Land Based Sludge Management Program, Phase 1 - Sludge Dewatering Facilities
New York City Department of Environmental Protection
Hazen & Sawyer P.C./Stone & Webster Engineering Corporation (Joint Venture)
General Contractors Association
1995 New Croton Gatehouse and Temporary Construction Cofferdam
Mergentime Corp./J.F. White Contracting Corp. (Joint Venture)
1994 Reconstruction of the World Trade Center
Karl Koch Erecting Corp.
Slattery Associates Inc.
H. Sand & Co., Inc.
1993 Morton Street Emergency Exit and Ventilation Shaft
Perini Corp.
1992 Empire Railway Connection Project
Delmar Construction Company
1991 Construction of the LIE Collector and Distributor Roads beneath the LIRR, Queens
New York State Department of Transportation
Andrews & Clark
Slattery Associates, Inc.
1990 Rehabilitation of the FDR Drive between 79th & 90th Streets
John P. Picone, Inc.
1989 Archer Avenue Subway
General Contractors Association
1988 Mid-Manhattan Water Tunnel
New York City Board of Water Supply
Martin Hauptman
1987 North River Water Pollution Control Project
New York City Department of Environmental Protection
General Contractors Association
1986 Statue of Liberty Restoration
Lehrer/McGovern, Inc.
1985 Rehabilitation of the FDR Drive - South Street Viaduct
New York State Department of Transportation
New York City Department of Transportation
Blauvelt Engineering Co.
P.R.C. Harris Inc.
Yonkers Contracting Co., Inc.
1984 Trump Tower
Trump Equitable
Fifth Avenue Co.
Swanke Hayden Connell
HRH Construction Co.
1983 Lexington Avenue Station of the 63rd Street Subway Tunnel
Schiavone Contracting Co.
Impresit-Girola-Lodgiani
Crimmins Contracting Co.
1982 Beth Israel Medical Center Expansion & Modernization Project
R. Rosenwasser
Schumann, Lichtenstein & Claman
W.J. Barney
1981 Palace Hotel
Irwin G. Cantor
Emery Roth
Dic Underhill
Morse Diesel
Helmsley Spear
1980 Bowery Bay Waste Water Treatment Plant
Horn Construction
1979 Hempstead Resources Recovery Facility
Charles Velzy Assoc.
Parsons & Whittemore
Town of Hempstead
1978 Citicorp Center
HRH Construction Corp.
LeMessurier Associates
Emery Roth & Sons
1977 Archer Avenue Subway
Emanuel Ciminello, Sr.
1976 Roosevelt Island
David I. Ozerkis
1975 North Branch Intercepting Sewer, Contract 3
Terence G. McKusker
1974 Waterside Housing Development
Richard Ravitch
1973 63rd Street Tunnel
Clark Hestmark
1972 Bruckner Interchange
John D. Saunders
1968 Middle Income Housing
Alfonso A. DiMeo
1966 Lincoln Center
Col. William Powers